There's Tile in the Break Room!


Most of the flooring is complete throughout the fifth floor!

But most importantly is...


Nicole's entrance.:)


Nicole's floor.:)

and corner (complete with plugs and random hole in the wall.) Hope this was good enough!:)

Moving on...

Wall covering and tile in the restrooms are complete.


Paint and carpet in Dr. Mauger's office are complete.

Paint and carpet in Karen's office is complete.

Exam room flooring...check.
Conference room look-out.
Carpet in faculty hallway...check.
Still coming together...

Notice the lighting and the more finished look of the soffits. (As well as the new design element on the walls!)
Check-in

Patient waiting area.
Getting closer!